Quantitative Aptitude · Time and work
If 8 workers finish in 6 days, how many days for 12 workers?
Medium
- A3
- B4
- C5
- D6
Show answer and explanationAnswer and explanation
Correct answer: B. 4
The job takes 8 × 6 = 48 worker-days. With 12 workers it takes 48 ÷ 12 = 4 days.