If 8 workers finish in 6 days, how many days for 12 workers?

Medium
  1. A3
  2. B4
  3. C5
  4. D6
Show answer and explanation
Correct answer: B. 4

The job takes 8 × 6 = 48 worker-days. With 12 workers it takes 48 ÷ 12 = 4 days.